CONSTRUCTION OF NEW GAS TURBINES

CONSTRUCTION OF NEW GAS TURBINES

CONSTRUCTION OF NEW GAS TURBINES 600 450 ESOTECH

Works on the project: Construction of new gas turbines 40–70 MW for the Brestanica Thermal Power Plant, under the contracts for LOT 1 and LOT 3, which started almost exactly one year ago and are in the final phase.

Concluding activities are currently taking place, such as:

  • Testing and participation in the launch of the cooling system, automatic changeover control for internal load and supply of liquid fuel (KOEL);
  • Covering of cable routes;
  • Replacement of cable trays with larger cable trays;
  • Small electrical installation works (management of cables, labelling);
  • Documentation acquisition process (operation and maintenance manual, evidence of reliability of works).

An expert technical inspection of the entire project to construct the gas generator was successfully carried out on 7 March 2018. In his speech the project manager praised all contractors for the professional attitude, good implementation of works as well as timely execution of all contractual obligations.

It was established that there are no obstacles for the technical inspection which the contracting authority intends to carry out in the first week of April 2018. The contractors have enough time to implement all necessary works and activities by that date. There are no difficulties regarding the scope of our work under both contracts, because the activities have been almost completed.